Dat Hoa Binh Duong Plastic – PE Stretch Film Factory is a stunning project celebrating 27 years of establishment and development of Dat Hoa Co., Ltd., marking the success of the plastic pipe industry brand in Vietnam when gaining the trust of consumers across the country. This large-scale project is the expected cooperation opportunity of CBC, the leading Design & Construction contractor in Vietnam and Dat Hoa Plastic Co., Ltd.

1. Project overview

Project’s name

DAT HOA PLASTIC PROJECT

Investment owner

Dat Hoa Co., Ltd

Project location

Lot C-1-CN Road NA4, My Phuoc 2 Industrial Park, Ben Cat Town, Binh Duong Province

Contractor

Construction contractor: CBC

Total area

1620m2

Total volume of steel (tons)

31,132 tons

Execution time

42 days

2. Dat Hoa Co., Ltd

Dat Hoa Co., Ltd. was officially established in 1993 in Ho Chi Minh City. During 27 years of development, the company’s orientation and production scale have considerably increased. Hence, Dat Hoa has become a reputable supplier of the leading plastic pipe industry in Vietnam. With huge human resources, Dat Hoa Co., Ltd always has a team of highly specialized technicians to expand the company in three provinces, namely Ho Chi Minh City, Binh Duong and Quang Nam.

Understanding the economy's trend of Industrialization - Modernization, Dat Hoa has proved their position in the international race with a series of high-quality certified plastic products, and exported to many countries such as Australia, USA, Japan and Cambodia. Dat Hoa Group has deservedly become one of the leading companies in the field of manufacturing and trading plastic pipes serving in much civil and industrial construction such as agriculture, forestry, aquaculture in Vietnam. Along with its mission, Dat Hoa Co., Ltd. has been providing good quality products and perfect services at reasonable prices to satisfy the diverse needs of customers around the world.

Until now, the "big man" Dat Hoa is always striving to make new breakthroughs. Specifically, Dat Hoa Plastic is constantly expanding production scale, investing in modern equipment for factories with automatic technology lines to distribute throughout the Vietnam market.

3. Project details

CBC (Design & Construction contractor) has proved themselves as a high-qualified contractor when coordinating with Dat Hoa Co., Ltd. in completing the project. After the process of completion and construction supervision, the engineers considered that this is a project with a medium complexity. Specifically, within 6 weeks, the technical team had a meticulous plan to supervise the work to ensure the highest quality for each factory.

To ensure the safety for each stage of the factory construction, the design team applies careful insulation methods to be suitable with electromagnetic waves and the long wavelengths of energy. This is the key factor to serve the need of the high temperatures caused by weather. The factory must meet strict standards in terms of load, tonnage of steel and main structures to be successful when put into operation. Project details are as follows:

No.

Category

Start

Finish

1

Total progress of steel structure

25/06/2020

05/09/2020

2

Preparation

25/6/2020

08/07/2020

3

Sign the contract

25/06/2020

29/06/2020

4

Deploying the manufacturing drawing 

25/06/20 

8/7/2020

5

Steel structure processing

8/7/2020

22/7/2020

6

Main structure and purlins, roof corrugated iron, ordinary corrugated iron

8/7/2020

22/7/2020

7

Delivery of steel structures

23/7/2020

4/8/2020

8

Main structure and purlin

23/07/2020

25/07/2020

9

Corrugated iron roof

3/08/20 20

4/8/2020

10

Accessories (garbage guard)

3/8/2020

4/8/2020

11

Steel structure erection plan

26/07/2020

5/9/2020

12

Plan for erection of main structure and purlin

26/07/2020

9/8/2020

13

Plan to erect roof corrugated iron and gutters

5/8/2020

19/8/2020

14

Plan to install corrugated iron wall

15/8/2020

29/8/2020

15

Plan to erect canopy, roof drainage, trim, frill

30/8/2020

5/9/2020

16

Completion

27/8/2020

5/9/2020

4. Detailed pictures of project construction

dat hoa plastic project

DAT HOA PLASTIC is a project that achieved great expectations from the CBC team and Dat Hoa Co., Ltd. With a period of 6 weeks of non-stop working, the results of the project demonstrate a commendable spirit of cooperation when actively promoting work and completing the project on time. The factory is a great result of the "big man" Dat Hoa's trust in CBC, this project will bring the factory to achieve its ambitions in the plastic industry in the international market

最新博客
https://bmbsteel.com.vn/storage/2026/08/12740/dsc05507.jpg
1小时前
2026年8月7日上午,BMB Steel总部,BMB爱心学校基金会举办了第二季“逆风而行”企业感恩活动,旨在感谢那些信任、分享并与基金会一同携手,为在困难地区的儿童带来学习机会的企业。
https://bmbsteel.com.vn/storage/2026/08/12730/dsc05372.jpg
3天前
2026年7月31日,BMB钢铁公司为隆富1号热电厂T08标段的管架结构项目举办了首次切割仪式。
https://bmbsteel.com.vn/storage/2026/07/12707/dsc04831.jpg
1周前
2026年7月25日,BMB 2026三球台球赛在热烈的气氛中举行,吸引了众多员工和嘉宾的参与.
https://bmbsteel.com.vn/storage/2026/07/12700/1784898039056-4795261115143815487-4795261115143815487-b2a893de274c815e46166f8f407920bc.jpg
2周前
在2026年7月23日和24日,BMB钢铁公司参加了由胡志明市建筑大学建筑系组织的建筑工程师和建筑管理工程师毕业设计保护与评审活动。这是一项有意义的活动,旨在加强学校与企业之间的联系,同时提升培训质量,以满足建筑行业发展的需求。
https://bmbsteel.com.vn/storage/2026/07/12693/zy95z2hcvgvkznfwasteazrgzzzps292uxl2bg8vckrqk2r6zzvethherdftegzuwmtkbxlhrmxzuwmxwvdazg95awhsbta9.jpg
2周前
2026年7月24日,河内BMB钢铁公司的年轻工程师们参加了在中央血液学医院举行的志愿献血活动,为传播人道精神和对社区的责任感贡献了一份力量。
评论 (0)
HOTLINE
(+84) 767676170
CONTACT US
NOW