DAT HOA PLASTIC PROJECT

05-22-2022

Dat Hoa Binh Duong Plastic – PE Stretch Film Factory is a stunning project celebrating 27 years of establishment and development of Dat Hoa Co., Ltd., marking the success of the plastic pipe industry brand in Vietnam when gaining the trust of consumers across the country. This large-scale project is the expected cooperation opportunity of CBC, the leading Design & Construction contractor in Vietnam and Dat Hoa Plastic Co., Ltd.

1. Project overview

Project’s name

DAT HOA PLASTIC PROJECT

Investment owner

Dat Hoa Co., Ltd

Project location

Lot C-1-CN Road NA4, My Phuoc 2 Industrial Park, Ben Cat Town, Binh Duong Province

Contractor

Construction contractor: CBC

Total area

1620m2

Total volume of steel (tons)

31,132 tons

Execution time

  42 days

2. Dat Hoa Co., Ltd

Dat Hoa Co., Ltd. was officially established in 1993 in Ho Chi Minh City. During 27 years of development, the company’s orientation and production scale have considerably increased. Hence, Dat Hoa has become a reputable supplier of the leading plastic pipe industry in Vietnam. With huge human resources, Dat Hoa Co., Ltd always has a team of highly specialized technicians to expand the company in three provinces, namely Ho Chi Minh City, Binh Duong and Quang Nam.

Understanding the economy's trend of Industrialization - Modernization, Dat Hoa has proved their position in the international race with a series of high-quality certified plastic products, and exported to many countries such as Australia, USA, Japan and Cambodia. Dat Hoa Group has deservedly become one of the leading companies in the field of manufacturing and trading plastic pipes serving in much civil and industrial construction such as agriculture, forestry, aquaculture in Vietnam. Along with its mission, Dat Hoa Co., Ltd. has been providing good quality products and perfect services at reasonable prices to satisfy the diverse needs of customers around the world.

Until now, the "big man" Dat Hoa is always striving to make new breakthroughs. Specifically, Dat Hoa Plastic is constantly expanding production scale, investing in modern equipment for factories with automatic technology lines to distribute throughout the Vietnam market.

3. Project details

CBC (Design & Construction contractor) has proved themselves as a high-qualified contractor when coordinating with Dat Hoa Co., Ltd. in completing the project. After the process of completion and construction supervision, the engineers considered that this is a project with a medium complexity. Specifically, within 6 weeks, the technical team had a meticulous plan to supervise the work to ensure the highest quality for each factory.

To ensure the safety for each stage of the factory construction, the design team applies careful insulation methods to be suitable with electromagnetic waves and the long wavelengths of energy. This is the key factor to serve the need of the high temperatures caused by weather. The factory must meet strict standards in terms of load, tonnage of steel and main structures to be successful when put into operation. Project details are as follows:

No.

Category

Start

Finish

1

Total progress of steel structure

25/06/2020

05/09/2020

2

Preparation

25/6/2020

08/07/2020

3

Sign the contract

25/06/2020

29/06/2020

4

Deploying the manufacturing drawing 

25/06/20 

8/7/2020

5

Steel structure processing

8/7/2020

22/7/2020

6

Main structure and purlins, roof corrugated iron, ordinary corrugated iron

8/7/2020

22/7/2020

7

Delivery of steel structures

23/7/2020

4/8/2020

8

Main structure and purlin

23/07/2020

25/07/2020

9

Corrugated iron roof

3/08/20 20

4/8/2020

10

Accessories (garbage guard)

3/8/2020

4/8/2020

11

Steel structure erection plan

26/07/2020

5/9/2020

12

Plan for erection of main structure and purlin

26/07/2020

9/8/2020

13

Plan to erect roof corrugated iron and gutters

5/8/2020

19/8/2020

14

Plan to install corrugated iron wall

15/8/2020

29/8/2020

15

Plan to erect canopy, roof drainage, trim, frill

30/8/2020

5/9/2020

16

Completion

27/8/2020

5/9/2020

4. Detailed pictures of project construction

dat hoa plastic project

DAT HOA PLASTIC is a project that achieved great expectations from the CBC team and Dat Hoa Co., Ltd. With a period of 6 weeks of non-stop working, the results of the project demonstrate a commendable spirit of cooperation when actively promoting work and completing the project on time. The factory is a great result of the "big man" Dat Hoa's trust in CBC, this project will bring the factory to achieve its ambitions in the plastic industry in the international market

LATEST BLOGS
https://bmbsteel.com.vn/storage/2024/03/9567/dji-fly-20230901-110632-507-1693541386267-photo.jpg
3 weeks ago
FM Logistics is one of the leading "giants" in the shipping industry today. This company was established in the 1960s. Up to now, the reputation of FM Logistics is still known and trusted by customers.
https://bmbsteel.com.vn/storage/2024/03/9443/dji-fly-20230830-123812-479-1693374332803-photo.jpg
1 month ago
DH Logistic Network Vietnam is one of BMB's typical projects around mid-2022. The investor is Daiwa House Vietnam Co., Ltd., part of Daiwa House Industry Japan, one of the "fastidious" investors that BMB is accompanied by.
https://bmbsteel.com.vn/storage/2024/01/9150/dji-fly-20230823-121834-993-1686118060605-photo-edit.jpg
3 months ago
Nam Ha Footwear Factory is one of the large and highly complex projects for which BMB is honored to be the main contractor. This factory project has a total area of up to 155,000 m2 and uses nearly 2,000 tons of steel to serve it. Understanding the importance and expectations of the investor, Nam Ha Shoes Factory Co., Ltd.,
https://bmbsteel.com.vn/storage/2023/12/8994/2-medium.jpg
4 months ago
The project " Lube Oil Blending Plant and Tank Farm Terminal " is located in Ong Keo Industrial Park, Nhon Trach District, Dong Nai Province. As a province that is no stranger to us, with a large area and favorable geographical position for tourism and economic exploitation, Nhon Trach Industrial Park quickly rises and is at the "top" of the largest industrial park in the Southeast region.
https://bmbsteel.com.vn/storage/2023/12/8969/nha-may-det-thanh-cong-giai-doan-1.gif
4 months ago
Converging all the necessary elements of a modern industrial park, Hoa Phu Industrial Park, invested in by Hoa Phu Joint Stock Company, is considered one of the ideal locations for domestic and foreign businesses in the country when looking for investment opportunities in Vinh Long. The project "Thanh Cong Textile Factory" is also one of the projects chosen by Thanh Cong Textile Garment Investment Trading Joint Stock Company in Hoa Phu Industrial Park to stop. Below is the detailed article on the project "Thanh Cong Textile Factory".