DAT HOA PLASTIC PROJECT

05-21-2022

Dat Hoa Binh Duong Plastic – PE Stretch Film Factory is a stunning project celebrating 27 years of establishment and development of Dat Hoa Co., Ltd., marking the success of the plastic pipe industry brand in Vietnam when gaining the trust of consumers across the country. This large-scale project is the expected cooperation opportunity of CBC, the leading Design & Construction contractor in Vietnam and Dat Hoa Plastic Co., Ltd.

1. Project overview

Project’s name

DAT HOA PLASTIC PROJECT

Investment owner

Dat Hoa Co., Ltd

Project location

Lot C-1-CN Road NA4, My Phuoc 2 Industrial Park, Ben Cat Town, Binh Duong Province

Contractor

Construction contractor: CBC

Total area

1620m2

Total volume of steel (tons)

31,132 tons

Execution time

42 days

2. Dat Hoa Co., Ltd

Dat Hoa Co., Ltd. was officially established in 1993 in Ho Chi Minh City. During 27 years of development, the company’s orientation and production scale have considerably increased. Hence, Dat Hoa has become a reputable supplier of the leading plastic pipe industry in Vietnam. With huge human resources, Dat Hoa Co., Ltd always has a team of highly specialized technicians to expand the company in three provinces, namely Ho Chi Minh City, Binh Duong and Quang Nam.

Understanding the economy's trend of Industrialization - Modernization, Dat Hoa has proved their position in the international race with a series of high-quality certified plastic products, and exported to many countries such as Australia, USA, Japan and Cambodia. Dat Hoa Group has deservedly become one of the leading companies in the field of manufacturing and trading plastic pipes serving in much civil and industrial construction such as agriculture, forestry, aquaculture in Vietnam. Along with its mission, Dat Hoa Co., Ltd. has been providing good quality products and perfect services at reasonable prices to satisfy the diverse needs of customers around the world.

Until now, the "big man" Dat Hoa is always striving to make new breakthroughs. Specifically, Dat Hoa Plastic is constantly expanding production scale, investing in modern equipment for factories with automatic technology lines to distribute throughout the Vietnam market.

3. Project details

CBC (Design & Construction contractor) has proved themselves as a high-qualified contractor when coordinating with Dat Hoa Co., Ltd. in completing the project. After the process of completion and construction supervision, the engineers considered that this is a project with a medium complexity. Specifically, within 6 weeks, the technical team had a meticulous plan to supervise the work to ensure the highest quality for each factory.

To ensure the safety for each stage of the factory construction, the design team applies careful insulation methods to be suitable with electromagnetic waves and the long wavelengths of energy. This is the key factor to serve the need of the high temperatures caused by weather. The factory must meet strict standards in terms of load, tonnage of steel and main structures to be successful when put into operation. Project details are as follows:

No.

Category

Start

Finish

1

Total progress of steel structure

25/06/2020

05/09/2020

2

Preparation

25/6/2020

08/07/2020

3

Sign the contract

25/06/2020

29/06/2020

4

Deploying the manufacturing drawing 

25/06/20 

8/7/2020

5

Steel structure processing

8/7/2020

22/7/2020

6

Main structure and purlins, roof corrugated iron, ordinary corrugated iron

8/7/2020

22/7/2020

7

Delivery of steel structures

23/7/2020

4/8/2020

8

Main structure and purlin

23/07/2020

25/07/2020

9

Corrugated iron roof

3/08/20 20

4/8/2020

10

Accessories (garbage guard)

3/8/2020

4/8/2020

11

Steel structure erection plan

26/07/2020

5/9/2020

12

Plan for erection of main structure and purlin

26/07/2020

9/8/2020

13

Plan to erect roof corrugated iron and gutters

5/8/2020

19/8/2020

14

Plan to install corrugated iron wall

15/8/2020

29/8/2020

15

Plan to erect canopy, roof drainage, trim, frill

30/8/2020

5/9/2020

16

Completion

27/8/2020

5/9/2020

4. Detailed pictures of project construction

dat hoa plastic project

DAT HOA PLASTIC is a project that achieved great expectations from the CBC team and Dat Hoa Co., Ltd. With a period of 6 weeks of non-stop working, the results of the project demonstrate a commendable spirit of cooperation when actively promoting work and completing the project on time. The factory is a great result of the "big man" Dat Hoa's trust in CBC, this project will bring the factory to achieve its ambitions in the plastic industry in the international market

最新博客
https://bmbsteel.com.vn/storage/2025/08/11527/dsc08347.jpg
1周前
最近,BMB钢铁胡志明市办公室有幸迎来了FM认证的代表,这是一家专注于安全和质量的国际知名认证机构,为我们的工程师和专业人员举办了一次内部培训会议。
https://bmbsteel.com.vn/storage/2025/08/11502/dsc08271.jpg
3周前
2025年8月2日上午,BMB爱心学校基金会前往平昌县垃圾填埋区,向贫困家庭赠送礼物,作为“微小行动-真实善良”活动的一部分。
https://bmbsteel.com.vn/storage/2025/07/11431/z6847827818873-4742abfd28b2d58ab93e32e36a2d785e.jpg
1个月前
7月25日,BMB钢铁参加了胡志明市建筑大学土木工程学院的毕业项目评审小组。
https://bmbsteel.com.vn/storage/2025/07/11404/dsc07207.jpg
1个月前
2025年7月19日,BMB公开台球锦标赛2025在LYP台球俱乐部(胡志明市富新区)举行,现场气氛活泼而充满激情,所有BMB钢铁成员热情高涨。
https://bmbsteel.com.vn/storage/2025/06/11228/phototrangbui-1738.jpg
2个月前
2025年6月7日(星期六)早上,BMB钢铁内部羽毛球锦标赛2025在充满团结和活力的生动愉快氛围中正式在POOC球场举行。
评论 (0)
HOTLINE
(+84) 767676170
CONTACT US
NOW