With 25 years experience in the market of water tanks and solar water heaters, Tan A Dai Thanh has magnificently become a familiar name for many Vietnamese people by virtue of its quality and long-standing brand reputation. Recently, BMB Steel had the opportunity to cooperate with Tan A Dai Thanh Group to execute a large-scale construction chain of 3 factories No. 4, 5 and 6 in Long An. In this article, let's explore with BMB Steel speciality about this 3-factory project.

1. Project overview

Name of project

Tan A Dai Thanh Factory Project - Factory No. 4, 5, 6

Investment owner

Tan A Dai Thanh Group Joint Stock Company

Project location

Tan A Dai Thanh Industrial Park, Duc Hoa, Long An

Contractors

BMB Steel

Total area

66000m2

Total weight of steel (tons)

804 123 tons

Execution time

145 days

2. Cooperation with the project investment owner: Tan A Dai Thanh Group Joint Stock Company

Formerly Dai Thanh Company (since 1990), with more than 26 years of experience, Tan A Dai Thanh has officially become a special name in the market of solar water heaters with more than dozens of large-scale production factories (up to 60000m2 area spreading across provinces and cities in Vietnam such as Ho Chi Minh City, Hanoi, Da Nang, Dak Nong, Hung Yen, etc.

Tan A Dai Thanh Group Joint Stock Company

In the development of the whole country, Tan A Dai Thanh group always strives to rise up in all aspects of the business to expand the distribution chain in Vietnam. With the business philosophy of "Always consider customer’s satisfaction when using our products and services as a measure of success", Tan A Dai Thanh has constantly changed and innovative technology to meet strict customer's requirements and serve the needs of international standards. The products at Tan A Dai Thanh always achieve the highest quality standards from the selection of raw materials, production, packaging and finishing products. Therefore, when reaching consumers, the products have obtained optimal quality.

In this day and age, Tan A Dai Thanh Group has made a strong breakthrough to develop into a leading economic group in Vietnam, operating in many industries. Specifically, along with water heaters, Tan A Dai Thanh has actively expanded its products to dozens of different types. The group's famous products can be mentioned as: STRMAN plastic pipes, shower faucets, wash basins, plastic butter, upstream water filters, etc.

3. Project details

With a rapid construction time (145 days) for the chain of 3 factories No. 3, 4, 5 of Tan A Dai Thanh Group, the project is officially marked in the series of achievements that BMB has implemented over the years. Through project completion and inspection, engineers determined that this is a project with medium complexity, but the huge scale and volume of steel (up to 66 000m2 and 804 124 tons) are two complicated factors. These intricate problems make the design team have to meticulously consider to come up with a suitable design plan, ensuring the capacity and function of each factory.

To ensure the temperature conditions of the factories’ "shield”, which protect the 3 plants from the effects of the environment, a corrugated iron system was applied to ensure the project’s optimization when completed. Specifically:

  • Roofing system: Bare Zinc – Alu AZ150

Waveform: seam lock.

Area: 64,784 m2.

  • Wall cladding: Bare Zinc – Alu AZ150

Waveform: 7 waves.

Area: 8,416 m2.

  • Polycarbonate Nicelight: Milky

Waveform: Seam-lock.

Area: 6,793 m2.

The quality corrugated iron system was installed suitably. Thus, when put into operation, the 3 factories have achieved many different standards, including standards of load, deviation, etc. In terms of construction progress, all 3 factories were built at the same time. Specifically, factory No. 4 conducted on June 3, 2017, factory No. 5 carried out on April 10, 2017 and factory No. 6 on March 27, 2017.

4. Detailed pictures of project construction 

Detailed pictures of project construction 1

Detailed pictures of project construction 2

With an enthusiastic and productive working spirit, BMB Steel's team from engineers, designers to workers worked together smoothly to promote the progress and complete the project on time. The trust from the investment owner Tan A Dai Thanh Group is the driving force for BMB Steel to strive to develop day by day to become a reputable and quality prefabricated factory, serving the needs of construction and expansion of business.

最新博客
https://bmbsteel.com.vn/storage/2024/06/9827/dji-fly-20230928-093144-652-1695868392954-photo.jpg
1年前
Entobel项目是BMB Steel在2023年的典型项目之一,面积为50000平方米,钢材为1000吨。
https://bmbsteel.com.vn/storage/2022/01/4376/du-an-maxihub-phan-ket-cau-thep-nha-xuong-da-hoan-thanh.jpg
3年前
BMB钢铁是Maxihub项目的主要承包商 - 投资方是台湾的中油公司。让我们更多了解这个项目!
https://bmbsteel.com.vn/storage/2021/10/4228/thub.gif
3年前
植物会所是一个小规模但高度复杂的项目。BMB钢铁公司细致地计算建筑的每一个细节,以达到最佳完美。要了解更多,让我们在下面的文章中与BMB钢铁公司一起探讨这一迷人的预制钢结构建筑!
https://bmbsteel.com.vn/storage/2021/09/3956/img-20210817-095613.gif
3年前
Proposed Warehouse Complex is a large-scale warehouse and factory project in the Philippines market. Let's learn more about this BMB Steel!
https://bmbsteel.com.vn/storage/2021/03/2985/central-group-toan-canh-ve-du-an-tong-kho-logistic-tai-thai-lan.png
4年前
After all challenges and difficulties in recent years, BMB Steel has excellently completed and handed over Logistic Warehouse in Thailand.
评论 (0)
HOTLINE
(+84) 767676170
CONTACT US
NOW