BMB Steel is proud to assist with the Dong Nai port-CFS project. Our works entailed the design, supply, fabrication, and erection of 160 tonnes of the steel structure.
Some parameters:
The Owner | : Dong Nai Port Corp |
Building Area | : 6,000 m2 |
Building and Use | : CFS Warehouse |
Location | : Dong Nai Port, Dong Nai Province |
Especially, the building features 70M clear span with a 10% slope. BMB Erection Team has an excellent performance in Schedule and Safety also. It takes only 5 days for finishing the frame, 5daysfor cladding works, and get ZERO ACCIDENT at the site.
Some site pictures for reference: